Project schedule

Project Schedule № SAMPLE-NX-PS-2026-018 · Custom project · final-assembly automation · ~14 months

What the client gets after contract signing — detailed delivery plan with owners and dependencies

NexumAutonomous Robotics
ANONYMISED SAMPLE · NEXUM

DOCUMENT

Project Schedule № SAMPLE-NX-PS-2026-018

Custom project · final-assembly automation · ~14 months

Project parameters

Contract
NX-2026-MFG-0009
Project type
Custom · multi-vendor
Start
1 June 2026
Finish
Q3 2027 (target)
Total duration
~14 months
Team
12 people (Nexum + OEM partners)

Detailed delivery plan for a custom final-assembly automation project. Covers 4 phases (Discovery → Engineering → Execution → Deployment), 18 key milestones, owner per step and dependencies. The schedule is attached to the contract and updated bi-weekly against the actual.

Project phases

4 phases · 18 milestones

PhaseDurationKey milestone
01 · Discovery2 moSite assessment
Nexum / Engineering
Site assessment report
01 · DiscoveryProcess simulation
Nexum / Engineering
Process model
01 · DiscoveryFeasibility + budget range
Nexum / Commercial
TEO · budget range
01 · DiscoveryBrief signed◇ critical
Client + Nexum
Signed brief
02 · Engineering3 moDetailed design
OEM partner + Nexum
Engineering package
02 · EngineeringContract + LC
Nexum / Legal
Signed contract + LC
02 · EngineeringOEM batch order◇ critical
Nexum / Sourcing
PO confirmed
02 · EngineeringMES alignment
Client IT + Nexum
Integration spec
03 · Execution5 moBatch production
OEM
Production report
03 · ExecutionPre-production check
Nexum / QC
Pre-production report
03 · ExecutionFactory Acceptance Test◇ critical
Nexum / QC
FAT report PDF
03 · ExecutionLogistics + customs◇ critical
Nexum / Logistics
Shipment + customs
04 · Deployment4 moInstallation + cabling
Nexum / Integration
Installation log
04 · DeploymentMES integration◇ critical
Nexum + Client IT
Integration sign-off
04 · DeploymentCommissioning + tests
Nexum / Engineering
Commissioning act
04 · DeploymentOperator training
Nexum / Training
Training sign-off
04 · DeploymentControlled go-live◇ critical
Client + Nexum
Go-live act
04 · DeploymentSwitch to service contract
Nexum / Service
SLA agreement

Critical path

Milestones the project deadline rests on

These 6 items can't be sped up by 2 weeks and can't be deferred without shifting everything downstream. If any of them stalls, we escalate.

  1. 01Brief sign-off — Engineering can't start without it. Common bottleneck: client-side internal alignment.
  2. 02OEM batch order — production runs 2—4 months. Early placement shortens total time.
  3. 03FAT — final checkpoint before shipment. Defects are replaced by the manufacturer within 2 weeks.
  4. 04Customs clearance — critical to verify documents 3—4 weeks before cargo arrival.
  5. 05MES integration — most common deployment-phase delay. Early collaboration with the client's IT team mitigates this.
  6. 06Controlled go-live — a 2-week gradual ramp-up to full load.

Schedule rules

  • The schedule is reviewed bi-weekly at the client status meeting.
  • Scope changes — via formal change request, fixed in a contract annex.
  • Risk buffer — 10—15% of total duration baked into Engineering and Deployment phases.
  • Final go-live date is locked at least 4 weeks ahead so the client can plan training and transition.

Signed by

Nexum Project Manager

Date

20 May 2026

This is an anonymised example. Real documents are tailored per client and contain specific particulars, prices and timelines. Request a full sample under NDA at the bottom of this page.