Project schedule
Project Schedule № SAMPLE-NX-PS-2026-018 · Custom project · final-assembly automation · ~14 months
What the client gets after contract signing — detailed delivery plan with owners and dependencies
DOCUMENT
Project Schedule № SAMPLE-NX-PS-2026-018
Custom project · final-assembly automation · ~14 months
Project parameters
Detailed delivery plan for a custom final-assembly automation project. Covers 4 phases (Discovery → Engineering → Execution → Deployment), 18 key milestones, owner per step and dependencies. The schedule is attached to the contract and updated bi-weekly against the actual.
Project phases
4 phases · 18 milestones
| Phase | Duration | Key milestone |
|---|---|---|
| 01 · Discovery | 2 mo | Site assessment Nexum / Engineering Site assessment report |
| 01 · Discovery | — | Process simulation Nexum / Engineering Process model |
| 01 · Discovery | — | Feasibility + budget range Nexum / Commercial TEO · budget range |
| 01 · Discovery | — | Brief signed◇ critical Client + Nexum Signed brief |
| 02 · Engineering | 3 mo | Detailed design OEM partner + Nexum Engineering package |
| 02 · Engineering | — | Contract + LC Nexum / Legal Signed contract + LC |
| 02 · Engineering | — | OEM batch order◇ critical Nexum / Sourcing PO confirmed |
| 02 · Engineering | — | MES alignment Client IT + Nexum Integration spec |
| 03 · Execution | 5 mo | Batch production OEM Production report |
| 03 · Execution | — | Pre-production check Nexum / QC Pre-production report |
| 03 · Execution | — | Factory Acceptance Test◇ critical Nexum / QC FAT report PDF |
| 03 · Execution | — | Logistics + customs◇ critical Nexum / Logistics Shipment + customs |
| 04 · Deployment | 4 mo | Installation + cabling Nexum / Integration Installation log |
| 04 · Deployment | — | MES integration◇ critical Nexum + Client IT Integration sign-off |
| 04 · Deployment | — | Commissioning + tests Nexum / Engineering Commissioning act |
| 04 · Deployment | — | Operator training Nexum / Training Training sign-off |
| 04 · Deployment | — | Controlled go-live◇ critical Client + Nexum Go-live act |
| 04 · Deployment | — | Switch to service contract Nexum / Service SLA agreement |
◇ Critical path
Milestones the project deadline rests on
These 6 items can't be sped up by 2 weeks and can't be deferred without shifting everything downstream. If any of them stalls, we escalate.
- 01Brief sign-off — Engineering can't start without it. Common bottleneck: client-side internal alignment.
- 02OEM batch order — production runs 2—4 months. Early placement shortens total time.
- 03FAT — final checkpoint before shipment. Defects are replaced by the manufacturer within 2 weeks.
- 04Customs clearance — critical to verify documents 3—4 weeks before cargo arrival.
- 05MES integration — most common deployment-phase delay. Early collaboration with the client's IT team mitigates this.
- 06Controlled go-live — a 2-week gradual ramp-up to full load.
Schedule rules
- The schedule is reviewed bi-weekly at the client status meeting.
- Scope changes — via formal change request, fixed in a contract annex.
- Risk buffer — 10—15% of total duration baked into Engineering and Deployment phases.
- Final go-live date is locked at least 4 weeks ahead so the client can plan training and transition.
Signed by
Nexum Project Manager
Date
20 May 2026
This is an anonymised example. Real documents are tailored per client and contain specific particulars, prices and timelines. Request a full sample under NDA at the bottom of this page.