FAT Report № SAMPLE-NX-FAT-2026-024

Pudu CC1 · 12-unit batch · Shenzhen factory

Contract
NX-2026-CL-0017
Manufacturer
Shenzhen Pudu Robotics
Inspection date
08—10 April 2026
Inspector
Nexum lead engineer
Inspection scope
100% (12/12)
Sampling method
Full inspection

Summary

Of 12 units, 11 are ready for shipment. One unit (S/N PCC1-2026-0008) showed a defect in the front-module brush during the functional test — replaced by the manufacturer before shipment. Replacement confirmation attached at the end of the report.

Total units
12
Passed inspection
11
Defects pre-fix
1
Defects post-fix
0

Serial numbers

Batch unit list

Serial numberFirmwareBatteryStatus
01PCC1-2026-0001v3.4.2OKPass
02PCC1-2026-0002v3.4.2OKPass
03PCC1-2026-0003v3.4.2OKPass
04PCC1-2026-0004v3.4.2OKPass
05PCC1-2026-0005v3.4.2OKPass
06PCC1-2026-0006v3.4.2OKPass
07PCC1-2026-0007v3.4.2OKPass
08PCC1-2026-0008v3.4.2OKReplaced
09PCC1-2026-0009v3.4.2OKPass
10PCC1-2026-0010v3.4.2OKPass
11PCC1-2026-0011v3.4.2OKPass
12PCC1-2026-0012v3.4.2OKPass

Checklist

What was inspected

Body and serial number markingPass
Packaging integrity and labellingPass
System power-up and initialisationPass
Base movement functional testPass
Brush and water-loop check1 defect — replaced
Sensor check (LIDAR, ultrasonic, cameras)Pass
Autonomy at 50% loadPass — 7.8 h (target ≥7 h)
Operating noise levelPass — 56 dB (limit ≤60 dB)
Factory firmware versionv3.4.2 (current)
In-box contents (passport, manual, charger, accessories)Pass

Evidence

What's attached to the report

  • 01Photos of serial-number plates per unit (12 photos)
  • 02Functional-test videos per unit (12 videos, 30—60 seconds each)
  • 03Photos of internal components after controlled package opening (3 sampled units)
  • 04Replacement confirmation for defective unit PCC1-2026-0008 from the manufacturer
  • 05Battery parameters sheet with autonomy measurements
  • 06Inspector's questions and comments list

Shipment release

Initially 11 of 12 units were ready for shipment. One unit (PCC1-2026-0008) was replaced by the manufacturer after a defect was identified. After replacement, the full 12-unit batch is cleared for shipment. The new unit serial is added to the Packing list and the original is removed. Shipment to the client per contract NX-2026-CL-0017 is recommended.

Signed by

Nexum Inspector · Shenzhen

Date

10 April 2026

This is an anonymised example. Real documents are tailored per client and contain specific particulars, prices and timelines. Request a full sample under NDA at the bottom of this page.

Request sample

Request the full sample under NDA

We'll show you the document structure on an anonymised example from a real project. No commitment from your side — so you know what you'll receive.