Skip to content
Blog
Guides8 min

FAT in 14 points: the factory acceptance checklist

FAT (Factory Acceptance Test) is the only moment defects get fixed for free, while the machine is still at the factory. Our working 14-point checklist inside.

Context: our engineer in Shenzhen runs acceptance on every batch before shipment. A machine takes forty minutes to two hours depending on class. The protocol with photos and video reaches the client while the batch is still on the floor.

Acceptance happens on the factory's premises: it needs a test track, a load-test bench and access to the parts warehouse. The date goes into the contract together with a penalty for “batch not ready on the agreed date” — without that line, FAT has a habit of sliding until shipping day, when there is nothing left to check and no time to check it.

F·01

Serials vs the contract

Nameplate numbers must equal the contract annex. Batch substitution is ruled out here.

F·02

Completeness vs packing list

Stations, remotes, cables, fasteners — checked before the box closes.

F·03

Firmware versions

Pinned and identical across the batch. “It will auto-update later” is not an answer.

F·04

Power-on and self-test

Cold start, clean diagnostics, empty error log.

F·05

Navigation on the test track

Aisles, turns, stopping in front of an obstacle.

F·06

Sensors and e-stops

Every sensor is hand-blocked; the emergency stop is physically pressed.

F·07

Load test

Rated weight on trays or gripper, motion under load, incline per spec.

F·08

Battery cycle

Charge-discharge with measurement: capacity and time against the datasheet.

F·09

Dock approach

Automatic docking ×3 in a row, with no helping hand.

F·10

Noise and vibration

Measured in motion plus a subjective check: rattle is heard before it is seen.

F·11

Cosmetics and panel gaps

Panels, seams, scratches. The machine ships to a client, not “to testing”.

F·12

Marking and battery papers

UN labels, Class 9, the UN38.3/MSDS set matches the cells.

F·13

Packing and bracing

Export crate, moisture protection, fixation. Checked before the seal.

F·14

Photo and video of every SN

Each machine passes key tests with its serial in frame. That is the protocol.

Video of every machine with its serial number in frame is not paranoia. It is the only language all sides of a future dispute understand.

Part 02

Why FAT, not incoming inspection at home

The objection we hear most: “we'll check it when it arrives”. The arithmetic disagrees. A machine that has cleared customs is legally imported: returning it to the factory means re-export — a new declaration, lithium batteries shipped back as dangerous goods, 6–10 weeks and hundreds of dollars per unit. All while you pay for storage and the project stands still.

The same defect caught at FAT is turned around with the factory's own resources: their shift, their parts warehouse, their shipping plan. A board swap takes hours, a panel respray a day, a full machine replacement a week. The cost asymmetry is so crude that FAT pays for itself even if it catches a defect in one batch out of ten. Our statistics say it catches more.

Part 03

What acceptance finds most often

Typical FAT findings, 12 months of our acceptance runs
FindingFrequency · per 100 machinesFix at the factoryIf caught after delivery
Mismatched firmware across the batch1130 minutesweeks of remote debugging
Cosmetics: scratches, panel gaps9a daya “that was the carrier” dispute
Missing stations and cables6added to the crateair-freight reorder, $300+ and a month
Battery capacity below datasheet4cell replacementa six-month warranty dispute
Battery papers for the wrong cell3a day to reissuecargo stuck at the port

Frequencies rounded. “After delivery” outcomes are real cases from before FAT became mandatory in our pipeline.

What FAT costs and who pays

In our deliveries FAT is not an option but a stage of the process: a staff engineer runs it, and the cost dissolves into the project budget. If you buy direct, third-party inspection in Shenzhen or Suzhou costs $250–500 per working day — on a five-machine batch that is 1–2% of the budget. Treat it as an insurance premium: it buys the most expensive surprises out of your future.

If the supplier refuses FAT

The refusal comes in three flavours: “we have our own QC, don't you trust us?”, “inspection will delay the shipment”, and “fine, but for a fee comparable to the machine”. All three mean the same thing: between you and the factory sits a link that has no interest in showing the workshop — or there is no workshop at all. A manufacturer confident in its line welcomes inspection: for them it is free proof of quality. The reaction to a FAT request is as diagnostic as a video call from the floor.

Takeaway

Who signs and what happens next

The protocol is signed by our engineer and the factory's representative; the client receives it before shipment, with the right to stop the batch. Any defect found is turned around on the spot — over a year, that is cheaper than any “we'll sort it under warranty” through customs. Hold every supplier to this checklist, including us.

FAT is one stage of the deal's mechanics

The buyer's guide covers FAT as its own chapter, with examples of what acceptance actually catches. The process page shows where this stage sits between request and launch.

Author · Nexum QC group · Shenzhen
Next step

Want to map this onto your site?

The two-minute audit suggests the right format — catalog, package or custom project. Or write to us directly: the conversation starts with your numbers, not a slide deck.